Engineering

OMRIX TEL AVIV
NEW CIP SYSTEM

Project

Outcome
1

Project Awarded in June 2016

2

Skid Package Awarded January 2017

3

Skid FAT Completed September 2017

4

Skid Delivered and Installed October 2017

Project

at a Glance

Hyde Engineering + Consulting designed, procured, and installed the new CIP System (3 skids) between June 2016 and October 2017.

About

Hyde Engineering + Consulting

Hyde Engineering + Consulting has been a global leader in process system design, commissioning, and FDA compliance for regulated industries since 1993.

Our Results

40 - 60%

Reduction in Chemical Consumption

45 - 70%

Increase in CIP System Availability

40 - 70%

Reduction in Water Consumption

1.5 - 2.5x

Increase in Manufacturing Throughput

Project

Goals

New CIP System

Procurement

Site Assistance